Enforcement of Charges

Table of Contents

Why Acting Quickly is Critical for Subcontractors

When subcontractors aren’t paid on time, one option available under legislation such as the Building Industry Fairness (Security of Payment) Act (in Queensland) or similar laws in other states is to lodge a notice of charge. This legal tool allows subcontractors to secure payment for work or materials supplied by essentially charging the money owed to them against funds the head contractor or principal holds for the project.

It’s a powerful right, however it comes with strict rules, tight deadlines, and serious consequences if those rules aren’t followed.

What is a Notice of Charge?

A notice of charge is a formal, legal notice sent by a subcontractor to a head contractor (and sometimes the project principal), advising that the subcontractor is owed money for work or materials provided.

Once served correctly, this notice prevents the head contractor from paying out money to anyone else for that work until the claim is resolved. In many cases, it can stop funds flowing down the contract chain until the matter is settled.

When the Amount is Disputed

Lodging a notice of charge does not guarantee payment. The head contractor or principal may dispute the amount claimed. This might happen because they:

  • Believe the work was incomplete or defective.
  • Argue that the claimed amount is higher than agreed.
  • Claim that variations were not authorised.
  • Assert that the subcontractor has already been paid.

The One Month Court Deadline

If the amounts claimed in the notice of charge are disputed, court proceedings must be started within one month from the date of the notice.

This means that the subcontractor has a very small window to:

  1. Gather all relevant evidence (contracts, invoices, timesheets, delivery dockets, variation approvals, etc.).
  2. Engage legal representation.
  3. File the necessary documents in court to begin formal proceedings.

If this deadline is missed, the notice of charge will generally lapse,  and with it, the subcontractor’s legal protection over the funds.

Why the Deadline Matters

Construction projects move quickly. Once progress payments are made to contractors, the funds can flow to multiple parties in the payment chain. If a subcontractor misses the court deadline, the head contractor can legally release those funds to other subcontractors, suppliers, or themselves.

Without the security of the notice of charge, the unpaid subcontractor may be left chasing payment from a party who has already spent the money, and who may no longer have the financial means to pay.

Why You Should Seek Legal Advice First

Submitting a notice of charge is not a simple paperwork exercise. It is a formal legal process that can trigger disputes, court action, and potential counterclaims. Seeking legal advice from a construction lawyer before serving a notice of charge can help you:

  • Confirm you’re eligible to lodge a notice of charge.
  • Ensure the notice is completed correctly and served on the right parties.
  • Understand the risks if the claim is disputed.
  • Plan for the possibility of going to court.
  • Avoid making procedural mistakes that could invalidate your claim.

For example, if you lodge a notice without having sufficient documentation, you might find yourself in court within weeks with no strong evidence to back up your position. That can lead to losing the case, and being ordered to pay the other side’s legal costs.

Practical Tips for Subcontractors

If you’re considering lodging a notice of charge, here are some practical steps to protect yourself:

  1. Keep accurate records Always have a signed contract, approved variations, and documented proof of work done.
  2. Act quickly Timeframes start ticking from the day the notice is served, not when a dispute arises.
  3. Seek professional help A construction lawyer can prepare and serve the notice correctly, and be ready to act if a dispute is raised.
  4. Budget for legal costs If the matter is disputed, you may need to commit resources to litigation within a month.
  5. Know your legislation Laws vary between states, so ensure you’re following the right process for your jurisdiction.

A notice of charge can be a strong tool to protect subcontractors from non-payment, however it’s not a guarantee of getting paid. If the claim is disputed, you may find yourself in court within a matter of weeks, and missing the one-month deadline can mean losing your rights entirely.

The safest approach is to seek legal advice before you serve the notice. That way, you can ensure you meet all the requirements, prepare for any dispute, and protect your right to be paid for the work you’ve done.

For further information on your rights, visit beckerwatt.com.au

This article is general information, not legal advice for your situation. For advice on your matter, call 07 3269 4888 or send us a message.

Related Articles

If you’ve been given a payment claim and don’t plan to pay it in full, you must give the claimant [...]

A payment claim that misses one requirement can fail. And you may not find out until the other side pushes [...]

When building or renovating a home, one of the biggest decisions is the contract you sign with your builder. Two [...]

Send us a message

Tell us briefly what is happening and a construction lawyer will get back to you to talk it through.

  • 4.9 Google rating
  • $220 initial consultation
  • Confidential
This field is for validation purposes and should be left unchanged.
Name(Required)

Prefer to talk? Call 07 3269 4888