A payment claim that misses one requirement can fail. And you may not find out until the other side pushes back, weeks later.
Queensland’s Building Industry Fairness (Security of Payment) Act 2017 (the BIF Act) is strict about what a claim says, when you give it and how you give it. Get it right and you have a fast path to being paid. Get it wrong and you may have to start again.
This checklist shows you what a valid claim needs.
A valid claim is a written document that identifies the work, states one amount and asks for payment. You must give it on or after a reference date, within the time limit, to the right person, in the right way.
Who this checklist is for
This is for builders, subcontractors, suppliers and consultants on Queensland projects.
Two terms to know. The claimant is the person claiming payment. The respondent is the person who has to pay.
Part 1: What your claim must say
Section 68 of the BIF Act sets out the content. A payment claim for a progress payment must be a written document that:
- Identifies the work. Say which construction work, or which related goods and services, the claim covers.
- States the claimed amount. Give the amount you say is payable.
- Requests payment. Ask for the money.
- Includes any other prescribed information. The regulations can add requirements, so check the current rules.
Here is what that means in practice.
Be specific about the work. ‘Stage 2 works’ may not be enough. Say what you did, where and for which period.
Use one clear amount. Don’t give several competing totals. In MWB Everton Park Pty Ltd v Devcon Building Co Pty Ltd [2024] QCA 94, the Court of Appeal found a builder’s documents were not valid payment claims. One problem was that they did not state a single claimed amount.
Ask for payment. A document bearing the word ‘invoice’ is taken to meet this requirement. If it isn’t an invoice, make the request clear. A statement of account alone may not be enough.
You don’t need special wording. QBCC guidance says a claim can be made under the Act as long as it has the required information and is given on or after a valid reference date. Clear is still better than clever.
Part 2: When you can give it
The reference date
A reference date is the date from which you can make a claim. Your contract usually sets it. If it doesn’t, the Act sets a default, usually monthly.
Three rules to remember:
- You can’t give a claim before a reference date.
- You get one claim per reference date.
- A new claim can include amounts from an earlier claim.
The time limit
Section 75 sets the deadline. It depends on the type of claim.
Progress claims must be given before the end of the longest of:
- the period set by the contract, or
- 6 months after the work was last carried out, or the goods and services were last supplied.
Final payment claims get more time. The longest of these applies:
- the period set by the contract
- 28 days after the last defects liability period ends (the period after completion when defects must be fixed)
- 6 months after all the work is completed
- 6 months after all the goods and services are supplied
If the contract has ended, the position can change. Get advice early.
Part 3: How to give it
Section 75 says you give the claim to the person who is, or may be, liable to pay under the contract. For a subcontractor, that is usually the head contractor.
Section 102 then covers how. You can give the claim:
- the way your contract says, for example by email if the contract allows it, or
- the way section 39 of the Acts Interpretation Act 1954 (Qld) allows, such as personal delivery or post.
Some practical tips:
- Read the notice clause. Check the right address, email and person.
- Don’t assume email is safe. If the contract doesn’t allow it, there is risk. Queensland cases have raised doubt about whether email counts.
- Attach your documents. A download link on its own can cause problems.
- Keep proof. Save the sent email, delivery receipt or postage record, with the date and time.
Common mistakes that sink a claim
- Vague descriptions of the work
- Several different totals in one email or spreadsheet
- No clear request for payment
- Giving the claim too early, before the reference date
- A second claim for the same reference date
- Wrong recipient or wrong address
- Missing the time limit
- A licensing problem. If the work needed a QBCC licence and you didn’t hold one, you may not be able to recover payment
Your checklist before you send
- Read the contract for reference dates and notice rules.
- Confirm a reference date has arrived and no earlier claim used it.
- Describe the work clearly: what, where and when.
- State one claimed amount.
- Ask for payment, or make sure the document is an invoice.
- Add any prescribed information the regulations require.
- Check the time limit for your type of claim.
- Address it to the right respondent at the right address or email.
- Attach your documents and send them a permitted way.
- Save proof that you gave the claim.
- Check your licence covers the work.
The QBCC also publishes its own guidance on how to request payment. It is worth reading alongside this list.
What happens after you give the claim?
The respondent must either pay or respond with a payment schedule. That is usually due within 15 business days of getting the claim.
For the full journey from here, read our guide on what happens after you give your claim.
Not sure your claim stacks up?
A small error can cost you a claim. We help builders and subcontractors across Brisbane, the Gold Coast, the Sunshine Coast and the rest of Queensland.
If you want a second pair of eyes before you send, talk to our construction law team. If licensing is the worry, we can help with a licensing problem too.
Book a time with our team or browse more guides for Queensland builders in our latest news.
This article is general information only and is not legal advice. The law changes, and every claim depends on its contract and facts. Speak to a lawyer about your own situation.
Read also: Payment claim and adjudication lawyers