In this guide
If you’ve been given a payment claim and don’t plan to pay it in full, you must give the claimant a payment schedule. The deadline is 15 business days, or sooner if your contract says so. Miss it and you can owe the full amount.
That is the short answer. This guide covers what to put in the schedule, how to count the days and what happens if you get it wrong.
Who this guide is for
This is for the person receiving a claim. That might be a head contractor, a principal or a developer.
Two terms to know. The respondent is the person who has to pay. The claimant is the person asking for payment.
Read also: Payment claim and adjudication lawyers
What is a payment schedule?
A payment schedule is your written reply to a payment claim under Queensland’s Building Industry Fairness (Security of Payment) Act 2017 (the BIF Act).
It does three jobs:
- Identifies the claim you are replying to.
- States the amount you will pay. This is called the scheduled amount. It can be less than the claim, or even nil.
- Gives your reasons if you are paying less than the claimed amount.
If you plan to pay the claim in full by the due date, you don’t need a schedule. If you don’t, you do.
How long do you have to respond?
Section 76 of the BIF Act gives you whichever of these ends first:
- the time set by your contract, if it sets one
- 15 business days after the claim is given to you
Your contract can set a shorter time. It can’t give you a longer one.
Count business days carefully. They don’t include weekends or public holidays. They also don’t include the period from 22 December to 10 January. Check the current definition in the Act before you rely on a date.
Start counting from when the claim is given to you, not from when you first read it.
What must your payment schedule include?
The QBCC says a payment schedule must identify the claim and state all your reasons for paying less.
Use this list:
- Name the claim. Refer to the claim or invoice by date, number or both.
- State the scheduled amount. Give a clear figure, even if it is nil.
- List every reason. Be specific about what you are withholding and why.
- Put it in writing. Keep it clear and easy to follow.
Reasons can include retention you are holding, or work you say was not done. Whatever your reasons are, write them all down now. If the claimant disputes your schedule, you may lose the chance to raise reasons you left out.
Don’t ignore a claim you think is invalid
It is tempting to ignore a claim that looks wrong. That can backfire.
The QBCC recommends responding to every payment claim. If you believe the claim has problems, say so in your schedule and give your reasons. You can read what makes a claim valid in our guide to what makes a claim valid.
When is payment due?
You must pay the scheduled amount by the due date.
Your contract usually sets the due date. If it doesn’t, the BIF Act default is 10 business days after the claim is given. For some building work, the QBCC Act also caps the time a contract can allow.
What if you don’t give a payment schedule?
This is where it gets costly. If you miss the deadline:
- You can become liable for the full claimed amount. Under section 77, it falls due on the due date.
- You generally can’t put your side in an adjudication response. That means you may have no say on the amount.
- The QBCC can act. It says failing to respond can lead to a fine.
The claimant can then choose to apply for adjudication or recover the amount as a debt in court. Adjudication is a fast, interim process run through the QBCC’s Adjudication Registry.
The claimant usually has 30 business days to apply for adjudication. That time runs from the later of the due date and the last day you could have given the schedule.
What if you give a schedule but don’t pay?
You must still pay the scheduled amount by the due date. If you don’t, the claimant can act on that amount too.
For an unpaid scheduled amount, the claimant generally has 20 business days after the due date to apply for adjudication.
For the full journey from claim to adjudication, read our guide to the full claims journey.
Your next steps checklist
- Write down the date the claim was given to you.
- Count 15 business days, or the shorter time in your contract.
- Check your contract for any earlier deadline and how to give notices.
- Decide the amount you will pay.
- List every reason for withholding any part of the claim.
- Give the schedule in a way the contract or the law allows.
- Pay the scheduled amount by the due date.
- Keep proof of when and how you gave it.
The QBCC has its own guide on how to respond to a payment request, including a payment schedule example.
When to get a lawyer
Get advice early if:
- The deadline is close or already passed
- The amount is large
- You think the claim is invalid
- You want to set off backcharges or other amounts
- You have received an adjudication application
We help builders, contractors and principals across Brisbane, the Gold Coast, the Sunshine Coast and the rest of Queensland.
If you want a second pair of eyes on your schedule, speak with our construction law team. We can also help with contract advice or a QBCC issue.
Book a time with our team or read more in our latest news.
This article is general information only and is not legal advice. The law changes, and every situation depends on its contract and facts. Speak to a lawyer about your own situation.
This article is general information, not legal advice for your situation. For advice on your matter, call 07 3269 4888 or send us a message.