Cost Plus Building Contracts in Queensland: How They Work and the Risks

Table of Contents
In this guide
  1. How a Cost Plus Contract Works
  2. When Are Cost Plus Contracts Used?
  3. The Risks for Homeowners
  4. The Disputes We See Under Cost Plus Contracts
  5. What To Insist On Before Signing
  6. Example: Owners Who Signed Without Advice
  7. Frequently Asked Questions
  8. Get Your Contract Reviewed Before You Sign

In a cost plus building contract, the owner pays the builder’s actual costs of labour and materials, plus an agreed margin or fee, instead of a fixed price. It can suit some projects, but it moves the risk of rising costs onto the owner, and it is behind many of the invoice disputes we see at Becker Watt Lawyers.

This guide explains how cost plus contracts work in Queensland, the disputes they lead to, and what to insist on before you sign one.

How a Cost Plus Contract Works

Under a fixed price contract, the builder carries the risk if the job costs more than expected. Under a cost plus contract, the owner does. The builder charges what the work actually costs, plus a margin, which may be a percentage of costs or a fixed fee.

Queensland law treats a contract as a cost plus contract when the final amount payable cannot be worked out accurately when the contract is signed, leaving aside prime cost items and provisional sums. For a domestic building contract over $3,300, the contract must still state how the price will be calculated, including the builder’s reasonable estimate of the contract price.

When Are Cost Plus Contracts Used?

Cost plus contracts are often used for renovations where the condition of the existing building is unknown, for custom or high-end homes where the design will keep changing, and for jobs that need to start before the design is finished.

“Really, it’s up to the homeowner,” says Conor Stensness, Associate at Becker Watt Lawyers. “That’s why it’s prudent for any homeowner, before signing a contract, to get advice from a qualified solicitor who practises in construction law.”

The Risks for Homeowners

  • No fixed price. The QBCC warns that final costs under cost plus contracts are often 50% to 100% higher than owners expected.
  • No home warranty cover for non-completion. Under the Queensland Home Warranty Scheme, non-completion cover is not available for cost plus or construction management contracts. If the builder fails part way through, you cannot claim the cost of finishing the job.
  • Large invoices with little explanation. The owner pays as costs are incurred, so a big invoice can arrive at any stage.
  • Arguments about what counts as a cost, and what the margin is charged on.

Read also: What are provisional sums?

The Disputes We See Under Cost Plus Contracts

“The biggest ones are blowouts, and the margins in the invoices,” Conor says.

A typical dispute starts when a homeowner is hit with a large invoice and does not understand why it is due. “Mostly because it is a cost plus contract, the builder is entitled to it, within reason and depending on what the contract says,” Conor explains. “On most occasions, nine out of ten, the builder is entitled to that payment.”

That is the hard part of these disputes. The owner feels overcharged, but the contract they signed allows the builder to pass on its costs plus the margin. The questions that matter are whether the costs are genuine, whether they are the kind of cost the contract allows, whether the margin has been applied correctly, and whether the builder has kept the records the contract requires.

What To Insist On Before Signing

Conor’s main point is time. “Many builders these days will give homeowners a very short timeframe to accept the price that was quoted,” he says. “They may say, for example, ‘You’ve got seven days, otherwise we’ll have to increase the price’, because of labour and materials.”

“If I was a homeowner being offered a cost plus contract, I’d ask the builder for extra time, so I can get proper legal advice, understand what it means, and if necessary have things changed.”

With that time, make sure the contract has:

  • A realistic written estimate of the total price, and how it was worked out.
  • A clear definition of “cost”, and what is excluded, such as the builder’s overheads, staff time and equipment.
  • The margin, as a fixed fee or a percentage, and what it applies to.
  • Records: copies of supplier and subcontractor invoices, timesheets and a running cost report with each claim.
  • Notice of overruns: a requirement that the builder tells you in writing as soon as costs are tracking above the estimate.
  • A cap or a fixed price option for parts of the work where possible.

Example: Owners Who Signed Without Advice

Conor says the pattern in these matters is the same. “I’ve had a lot of homeowners come to us who haven’t had any legal advice, and that’s why they are where they are.” By the time the invoices arrive, the terms are fixed and the options are narrower.

His advice is short: “Do your due diligence, and get legal advice before signing.”

Frequently Asked Questions

Are cost plus contracts allowed for homes in Queensland?

Yes, but they must meet the rules for domestic building contracts, including stating how the price is calculated and the builder’s reasonable estimate. Owners lose home warranty cover for non-completion under them.

Can I question a cost plus invoice?

Yes. You can ask for the supporting invoices and records the contract requires and dispute costs that are not allowed under it. Follow the contract’s process when you do.

Is a fixed price contract always better?

Not always. A fixed price contract gives certainty, but builders may price in more risk. The right choice depends on the project, and advice before signing helps you compare.

Get Your Contract Reviewed Before You Sign

If you have been offered a cost plus contract, or you are already facing invoices you do not understand, Becker Watt Lawyers can help. We review residential building contracts for homeowners and builders across Brisbane and the Gold Coast. Find out more about our building contract lawyers, or send us a message.

This article is general information, not legal advice for your situation. For advice on your matter, call 07 3269 4888 or send us a message.

Related Articles

Your builder has gone into liquidation and work on your home has stopped. It is one of the most stressful [...]

If you’ve been given a payment claim and don’t plan to pay it in full, you must give the claimant [...]

A payment claim that misses one requirement can fail. And you may not find out until the other side pushes [...]

Send us a message

Tell us briefly what is happening and a construction lawyer will get back to you to talk it through.

  • 4.9 Google rating
  • $220 initial consultation
  • Confidential
This field is for validation purposes and should be left unchanged.
Name(Required)

Prefer to talk? Call 07 3269 4888